ABB to Supply Electrical Equipment for Turkish Steel Plant
Posted on: Friday, 11 July 2008, 12:00 CDT
Swiss power and automation technology group ABB has won a $28 million contract to provide electrical equipment for a new steel plant in Turkey to ensure reliable power supply for high-quality production.
The project is reportedly the largest single private investment in the iron and steel industry in Turkey and will have the capacity to produce 2.5 million tons of hot flat-rolled products and 1.2 million tons of cold rolled products. The plant will also produce galvanizing steel, dyed sheet steel and rolled steel.
ABB will supply technology including a static var compensator (SVC), which compensates for fluctuations in the voltage and current of power supplies that can harm production quality in industrial plants.
The contract was awarded by MMK-Atakas, a joint partnership between Atakas Metallurgy and Port Management Turkey and Magnitogorsk Iron and Steel Works (MMK), a Russian company.
The order includes transformers, high and medium-voltage switchgear, a substation supervisory control and data acquisition system (SCADA), and flexible AC transmission system.
In addition to the SVC system, ABB will supply four power transformers, a 380/34.5kV complete turnkey switchyard, and a 72.5kV open switchyard. The company will also supply and install medium-voltage panels along with the SCADA and communications system.
Source: Datamonitor
Related Articles
- Liquid Computing Announces LiquidIQ 3.0 Unified Computing System Powered By Intel(R) Xeon(R) 5500 Series Processors
- Pharmaceutical Supply System Activates Rx Response for Second Time in 10 Days to Address Potential Impact From Hurricane Ike
- Pharmaceutical Supply System Activates Rx Response to Provide Single Point of Contact for Resolution of Pharmaceutical Supply Obstacles Associated With Hurricane Gustav
- Siemens, Stadtwerke Lubeck Commission Shoreside Power Supply System
- Wartsila to Supply 36MW Power Plant to Angolan Cement Works Facility
- Wartsila Contracted to Supply 100MW Power Plant for Installation in Togo
- PMA Members Testify at International Trade Commission Hot-Rolled Steel Hearing; Urge End to Duties Citing Steel Supply and Quality Problems
- Ranger Steel Supply Opens Tulsa Distribution Facility
- Sanyo to Replace Defective Parts in 12,500 Hot-Water Supply Systems
- China Draws Outline of State Energy Supply System
User Comments (1)
| 1. |
Posted by Mery on 11/15/2009, 23:32 pls contact to me directly aryasanattrading@yahoo.com |

RSS Feeds