Bear Creek provides project update: Engineering studies rapidly advancing to completion at Corani and Santa Ana silver deposits
Posted on: Wednesday, 1 April 2009, 08:30 CDT
The work completed to date on the Corani prefeasibility study ("PFS") demonstrates that the project has favorable development characteristics and metallurgical behavior that make for a straight-forward mining project with robust economics. Engineering and development work on Corani and Santa Ana has continued and will be accelerated now that the Rio Tinto obligation has been restructured and precious metals prices are improving. Importantly, in the face of strengthening silver prices, the Company now holds 410 million ounces of silver in measured and indicated resources along with a large base metal resource containing another 204 million ounces of equivalent silver.
The Company has a strong cash position with
The Company's flagship asset continues to be the Corani silver-lead-zinc deposit. The Corani PFS commenced in mid-2008 with the work being performed by Vector Engineering, Samuel Engineering and Independent Mining Consultants. Prior to initiating this study, the project was "right-sized" in order to focus on the higher-grade cores of the deposits at an optimum throughput rate with reduced capital and operating costs (see news release dated
The vast majority of the field studies were completed during 2008 and the engineering groups are now focusing on final processing design and costing studies. Additional cost to complete the pre feasibility is approximately
Metallurgical testing - During the past six months, activities have focused on extensive metallurgical testing at SGS Vancouver. Final testing is in progress on two "master" composite samples under optimized reagent and grinding conditions to conclude testing for the PFS. Test results are summarized as follows:
- 13 Locked cycle tests have been completed on different ore composites and blends. - Marketable concentrates were produced in all tests. Average concentrate grades are 56% lead, 1.9 kgs silver (lead concentrates) and 53% zinc, 470 g silver (zinc concentrates) with concentrate grades of 79% lead and 2.2 kgs being obtained on coarser sulfide ores. - No bulk concentrate will be produced, thus enhancing smelter payment terms. - Blending of sulfide ore with transitional ore shows that recoveries are basically additive. This represents a significant breakthrough as mine sequencing and stockpiling can be largely simplified with no adverse effect on overall recoveries. - Silver reports predominantly to the lead concentrate which optimizes smelter payment terms. - Recent addition of scavenger circuits in the test work has improved concentrate grades significantly with no detrimental effects to overall recoveries. Scavenger circuits are a low-capital cost common technology. - Leach optimization test work completed on two oxide ore composites which shows average silver recovery of 86%, with cyanide consumption of 1.5 kg/t. These excellent leach test results will be used to evaluate the treatment of lower grade oxide material in the outer deposit areas (later years) as well as potential treatment of oxide ores encountered during early mine-life, and possibly converting internal waste to ore, thus further reducing the stripping ratio - All material types contained within the deposits are now demonstrated to have a conventional metallurgical extraction process at recoveries in line with similar operating mines worldwide.According to
Santa Ana
Drilling continued at the Santa Ana silver heap leach project up to the end of the drilling season in
Highlights of the Santa Ana project are summarized below and are subject to further definition upon completion of the PEA:
- Low cost, open pit mining methods with low stripping ratios. - Mine sequencing in progress to optimize low-cash cost/ounce, particularly in early mine-life. - Metallurgical test work indicating 70% silver recoveries under heap leach conditions are completed for the PEA (see news release dated 21 July 2008). - Mine sequencing focusing on higher grade (55g/t Ag plus) silver pits over an up to 10 year mine life. - Low capital costs expected to be less than $50 million through the use of mobile crushers and contract mining - Annual production in the range of 4-6 million ounces silver at a 10,000 tpd throughput. - Favorable infrastructure and straight-forward permit path. - High leverage to silver prices with excellent opportunity to quickly access lower grade material in the event of higher silver prices. - Resource growth potential as under the expected plan only approximately one half of the total resource would be mined and untested exploration targets exist in the district. Note: Certain statements particularly with respect to expectations on capital and operating costs are subject to completion of the Santa Ana PEA. Mineral resources that are not mineral reserves do not have demonstrated economic viability.Mr. Swarthout summarizes as follows: "In short, Bear Creek's two silver deposits contain 410 million ounces of silver in the Measured and Indicated categories. Both projects are advancing to completion of their respective engineering studies by the middle of this year, placing Bear Creek's shareholders in a position to benefit from recently strong silver markets as these studies outline the economics of mining what we believe are amongst the best undeveloped silver deposits in the world."
RESOURCE TABLES Corani Deposit $9.35/tonne NSR cut-off and Prudent Open Pit Constraints; December 2007 ------------------------------------------------------------------------- Eq. Silver Lead Zinc Silver Mill- Mill- Mill- Mill- Eq. Silver Lead Zinc ion ion ion ion Silver Category Ktonnes Gm/t % % Ozs Lbs Lbs Ozs Gm/t ------------------------------------------------------------------------- Meas+Ind 248,421 40.9 0.73 0.45 327.1 3,976.8 2,467.7 531.2 66.5 ------------------------------------------------------------------------- Inferred 33,152 32.6 0.54 0.37 34.8 398.2 271.2 55.8 52.3 ------------------------------------------------------------------------- Note: Silver Equivalency calculated on 28/1/09 metal prices ($12.00/oz Ag, 0.51/lb Pb and 0.50/lb Zn. Recoveries of 80% for silver and 60% for both lead and zinc also assumed in the calculation. 1 oz Ag = 31.37 lb Pb and 1 oz Ag = 32.00 lb Zn. Silver equivalency only applied to Corani base metal resources. Santa Ana Deposit Based on 20 g/t Ag Cutoff and Prudent Open Pit Constraints; September 2008 ------------------------------------------------------------------------- Silver Lead Zinc Silver Lead Zinc Million Million Million Category Ktonnes Gm/t % % Ozs Lbs Lbs ------------------------------------------------------------------------- Measured 10,385 48.1 0.36 0.64 16.1 82.4 146.5 ------------------------------------------------------------------------- Indicated 45,592 45.1 0.33 0.56 66.1 331.7 562.9 --------- ------ ---- ---- ---- ---- ----- ----- ------------------------------------------------------------------------- Measured + Indicated 55,977 45.7 0.34 0.57 82.2 414.1 709.4 ------------------------------------------------------------------------- Inferred 23,333 50.3 0.32 0.51 37.7 164.6 262.3 ------------------------------------------------------------------------- Resource estimate was based on 47,436 meters of drilling in 260 diamond drill holes completed through July 2008 and was prepared by Independent Mining Consultants (IMC) of Tucson Arizona, with John Marek, P.E. acting as the Independent Qualified Person under NI 43 101 The TSX Venture Exchange does not accept responsibility for the adequacy or accuracy of this release.Regulatory footnotes:
All of Bear Creek's exploration programs and pertinent disclosure of a technical or scientific nature are prepared by or prepared under the direct supervision of
Certain disclosure in this release, including management's assessment of Bear Creek's plans and projects, constitutes forward-looking statements that are subject to numerous risks, uncertainties and other factors relating to Bear Creek's operation as a mineral exploration company that may cause future results to differ materially from those expressed or implied in such forward-looking statements. These risks, uncertainties and other factors are disclosed in Bear Creek's continuous disclosure filings with Canadian securities regulators including its most recent annual information form, available on www.sedar.com. Bear Creek expressly disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise.
SOURCE Bear Creek Mining Corporation
Source: PR Newswire
Related Articles
- Canadian Zinc Submits Permit Applications for Production at the Prairie Creek Mine
- Hecla Acquires 70.3% of Greens Creek Mine for $750 Million
- NovaGold's Rock Creek Mine Permit Upheld By Appeals Court
- Thompson Creek Announces Revised Reserves and New 10-Year Mine Plan for Thompson Creek Mine
- Canadian Zinc Corporation: Mineral Resources Confirmed and Upgraded at Prairie Creek Mine
- Quest Minerals & Mining Completes Mining Adjustment to Bring Higher Recovery
- Asian Dragon Group Inc. Enters Final Negotiations At World Renowned Tieluping Silver and Lead Mine
- Bear Creek Mining - More Positive Drill Results at Corani; Drilling Starts at La Curva
- Michigan Gold Announces the Presence of Significant Probable Silver Reserves in the Anita Mine
- Silver Wheaton Acquires More Shares of Bear Creek Mining Corporation
User Comments (0)

RSS Feeds