Capstone Reports Strong Production & Cash Operating Costs for the First Half of 2009
Posted on: Wednesday, 15 July 2009, 06:15 CDT
- 49.2 Million pounds of Copper in Concentrates With an Estimated Total
Cash Cost(1) of
Capstone Mining Corp. (CS: TSX) today announced its operating results for
the three and six months ended
"Capstone's two operations, the Cozamin and
Operational Highlights for the three and six months ended
The following is a summary of operational highlights for Capstone during
the second quarter and six months, respectively, ended
Operating Details - Cozamin Mine
Key operating statistics for the Cozamin Mine for the first and second quarter and year-to-date for 2009 are presented below:
------------------------------------------------------------------------- Q1 2009 Q2 2009 YTD 2009 ------------------------------------------------------------------------- Production(2) (contained in concentrates) ------------------------------------------------------------------------- - Copper (000s pounds) 9,812 9,881 19,693 ------------------------------------------------------------------------- - Lead (000s pounds) 1,155 2,331 3,486 ------------------------------------------------------------------------- - Zinc (000s pounds) 2,388 3,325 5,713 ------------------------------------------------------------------------- - Silver (ounces) 317,963 390,639 708,602 ------------------------------------------------------------------------- Mine ------------------------------------------------------------------------- - Tonnes of ore mined 248,507 243,494 492,001 ------------------------------------------------------------------------- Mill ------------------------------------------------------------------------- - Tonnes processed 248,325 249,975 498,300 ------------------------------------------------------------------------- - Tonnes processed per day 2,759 2,741 2,753 ------------------------------------------------------------------------- - Copper grade (%) 1.96 1.92 1.94 ------------------------------------------------------------------------- - Lead grade (%) 0.33 0.61 0.47 ------------------------------------------------------------------------- - Zinc grade (%) 0.81 1.01 0.91 ------------------------------------------------------------------------- - Silver grade (g/t) 56 66 61 ------------------------------------------------------------------------- Recoveries ------------------------------------------------------------------------- - Copper (%) 91.4 93.4 92.4 ------------------------------------------------------------------------- - Lead (%) 64.8 69.4 67.5 ------------------------------------------------------------------------- - Zinc (%) 53.9 59.5 56.5 ------------------------------------------------------------------------- - Silver (%) 71.0 73.6 72.5 ------------------------------------------------------------------------- Concentrate(2) ------------------------------------------------------------------------- - Copper (dmt) 18,461 17,595 36,056 ------------------------------------------------------------------------- - Copper (%) 24.1 25.5 24.8 ------------------------------------------------------------------------- - Silver (g/t) 463 561 511 ------------------------------------------------------------------------- - Lead (dmt) 782 1,500 2,282 ------------------------------------------------------------------------- - Lead (%) 67.1 70.5 69.4 ------------------------------------------------------------------------- - Silver (g/t) 1,738 1,511 1,589 ------------------------------------------------------------------------- - Zinc (dmt) 2,415 3,312 5,727 ------------------------------------------------------------------------- - Zinc (%) 44.8 45.5 45.2 ------------------------------------------------------------------------- On site Operating Costs (US$/t milled)(1) US$34.97 US$34.03 US$34.50 ------------------------------------------------------------------------- Total cash cost per pound of payable copper(1) US$1.00 US$0.81 US$0.90 ------------------------------------------------------------------------- (2) Adjustments based on final settlements will be made in future periods.Overall, the Cozamin Mine performed well, despite the Mexican Government ordered 5-day production interruption related to the H1N1 flu virus and shortages of feed related to delays in bringing the new, higher grade stopes on line. Development of very wide (20-30m) high grade areas of the Cozamin deposit were delayed because the wide mineralization extended deeper than anticipated from drilling and this mineralization needs to be extracted from the bottom up in order to ensure geotechnical stability. As a result, development had to be pushed deeper to get to the bottom of the high grade and, in the interim, production had to come from shallower areas with lower copper but higher lead content.
Development of the wider ore zones should be completed in Q3/09 and production is then expected to ramp up very quickly. In addition, access to mining areas to the west and to the east of the present zone will provide additional mining zones in Q3/09. Improved metallurgical performance since March, resulting from some improved reagents and regrinding of the copper-lead concentrate, has resulted in sustained higher copper recoveries (93.4% in Q2/09 vs. 91.4% in Q1/09) and concentrate grade (25.5% in Q2/09 vs. 24.1% in Q1/09), which performance is expected to be sustainable over the longer term but is not factored into the recently announced life-of-mine plan.
During the three months ended
Operating Details - Minto Mine
Key operating statistics for the Minto Mine for the first and second quarter and year-to-date for 2009 are presented below:
------------------------------------------------------------------------- Q1 2009 Q2 2009 YTD 2009 ------------------------------------------------------------------------- Production(3) (contained in concentrates) ------------------------------------------------------------------------ - Copper (000s lbs) 16,230 13,178 29,408 ------------------------------------------------------------------------- - Gold (oz)(2) 8,527 7,564 16,091 ------------------------------------------------------------------------- - Silver (oz) 101,991 64,927 166,918 ------------------------------------------------------------------------- Mining ------------------------------------------------------------------------- - Waste (tonnes) 2,196,728 2,845,300 5,042,028 ------------------------------------------------------------------------- - Ore (tonnes) 292,593 289,010 581,603 ------------------------------------------------------------------------- - Total material mined (tonnes) 2,489,321 3,134,310 5,623,631 ------------------------------------------------------------------------- Milling ------------------------------------------------------------------------- - Tonnes processed 233,529 267,254 500,783 ------------------------------------------------------------------------- - Tonnes processed per day 2,595 2,937 2,767 ------------------------------------------------------------------------- - Copper grade (%) 3.39 2.41 2.86 ------------------------------------------------------------------------- - Gold grade (g/t)(2),(3) 1.57 0.97 1.28 ------------------------------------------------------------------------- - Silver grade (g/t) 16.0 9.6 12.7 ------------------------------------------------------------------------- Recoveries ------------------------------------------------------------------------- - Copper (%) 93.0 92.6 93.0 ------------------------------------------------------------------------- - Gold (%)(2),(3), 72.8 71.9 72.0 ------------------------------------------------------------------------- - Silver (%) 83.5 79.6 81.7 ------------------------------------------------------------------------- Concentrate ------------------------------------------------------------------------- - Dry tonnes produced 17,283 14,667 31,950 ------------------------------------------------------------------------- - Copper grade (%) 42.6 40.8 41.6 ------------------------------------------------------------------------- - Gold grade (g/t)(2),(3) 15.53 12.5 13.9 ------------------------------------------------------------------------- - Silver grade (g/t) 183 139 162 ------------------------------------------------------------------------- On site Operating Costs(1) (US$/t milled)(4) US$47.85 US$44.52 US$46.01 ------------------------------------------------------------------------- Total cash cost per pound(1) of payable copper(4) US$0.86 US$1.08 US$0.96 ------------------------------------------------------------------------- (2) Gold is not assayed on site, resulting in a significant lag in receiving this data. (3) Adjustments based on final settlements will be made in future periods. (4) Minto's operating costs are adjusted to exclude mining of ore and waste not related to concentrate produced in the period, these costs are capitalized or inventoried in the financial statements, then expensed when the associated ore is processed.The Minto Mine exceeded budgeted Phase III throughput capacity in Q2/09, which budget factors in maintenance and availability versus the nominal design capacity of 3,200tpd. The Phase 3 North pit pushback was completed in March and attention was focused on stripping the Phase 3 South pushback and commencing the Phase 4 pit pushback, with mill production coming entirely from stockpiles throughout the quarter. As with prior pushbacks, the Minto Mine depletes stockpiles in grade order, from highest to lowest, until the high grade from the Phase 3 South pit pushback is accessed later in 2009. As noted above, excess water, over and above what could be contained in the water storage pond, was diverted into the open pit during freshet in order to prevent a non-compliant discharge. This diversion was anticipated in the budget for 2009. However, the snowpack was greater than usual, resulting in more water being diverted into the open pit than planned. The Minto Mine has received approvals from regulators to discharge approximately half of the excess water, and is doing so, and is working on the appropriate measures for the treatment and discharge of the remainder of the excess water. The timing of the discharge will affect the timing of re-entry into the open pit and therefore access to higher grade ore in the pit bottom. In the meantime, milling operations continue uninterrupted from available stockpiles and stripping of the Phase 4 pushback is well advanced and continuing. See 'Outlook' below.
During the three months ended
Outlook
As a result of the timing of a number of events at the Cozamin and
1. Completing access to the higher grade, very wide mining areas at the Cozamin Mine during Q3/09, which will result in mine production coming from slightly lower copper (but higher lead and zinc) grade areas until this highly productive area is fully developed. This could limit mill throughput to around design capacity, which is well below recently achieved throughput, but then should ramp up significantly in Q4/09.
2. Until the water is removed from the open pit, the Minto Mine will be restricted to processing stockpiled ore, of which there is sufficient to sustain operations for several months. As noted above, the Minto Mine is already discharging some of the excess water captured in the pit and is working on measures for the discharge of the remainder. High grade ore stripped in the Phase 3 south pit pushback was already exposed, drilled and blasted prior to the freshet inflow, but not removed from the pit, which ore will be readily available as soon as the water level is reduced to the level of the ore.
3. The Minto Mine has been working on a new water management plan for the
site for the past two plus years to address higher quantities of water within
the Minto Mine site than were anticipated in the original 1990's permitting
process. This plan should be submitted to regulators during
4. Waste stripping for the Phase 4 north pit pushback is proceeding on plan, which should expose ore in late 2009. As a result of both the Phase 3 south and Phase 4 north pushbacks nearing completion, the Minto Mine will have considerable high and medium grade ore available for processing in the latter part of 2009 and in 2010.
Overall, taking into the account the above items, combined with their
anticipated resolution and the proven capacity of both the Cozamin and
Second Quarter Financial Results Timing
Capstone will report its second quarter 2009 financial results on Thursday, August 13, 2009 and will host a conference call and webcast to discuss these results as noted below. Conference call and webcast details are as follows: Date: Friday August 14, 2009 Time: 8:00 AM PST (11:00 AM EST) Dial in: North America - 1-800-595-8550, International - 1-416-644-3422 Webcast: www.newswire.ca/en/webcast/viewEvent.cgi?eventID=2740540 Replay: North America - 1-877-289-8525, International - 1-416-640-1917 Replay Pass code:21311141 followed by number sign.The TSX does not accept any responsibility for the adequacy or accuracy of this press release.
(1) These are non-GAAP performance measures and readers should refer to Non-GAAP Performance Measures note at the end of this news release for further details.
Forward-Looking Information
This document may contain "forward-looking information" within the meaning of Canadian securities legislation and "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 (collectively, "forward-looking statements"). These forward-looking statements are made as of the date of this document and Capstone Mining Corp. (the "Company") does not intend, and does not assume any obligation, to update these forward-looking statements, except as required under applicable securities legislation.
Forward-looking statements relate to future events or future performance and reflect Company management's expectations or beliefs regarding future events and include, but are not limited to, statements with respect to the estimation of mineral reserves and resources, the realization of mineral reserve estimates, the timing and amount of estimated future production, costs of production, capital expenditures, success of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims and limitations on insurance coverage. In certain cases, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" or the negative of these terms or comparable terminology. By their very nature forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, risks related to actual results of current exploration activities; changes in project parameters as plans continue to be refined; future prices of resources; possible variations in ore reserves, grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of development or construction activities; as well as those factors detailed from time to time in the Company's interim and annual financial statements and management's discussion and analysis of those statements, all of which are filed and available for review on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on forward looking statements.
43-101 Compliance
Unless otherwise indicated, Capstone has prepared the technical
information in this news release ("Technical Information") based on
information contained in the technical reports and news releases
(collectively the "Disclosure Documents") available under Capstone Mining
Corp.'s and Sherwood Copper Corp.'s company profile on SEDAR at
www.sedar.com. Each Disclosure Document was prepared by or under the
supervision of a qualified person (a "Qualified Person") as defined in
National Instrument 43-101 - Standards of Disclosure for Mineral Projects of
the Canadian Securities Administrators ("NI 43-101"). Readers are encouraged
to review the full text of the Disclosure Documents which qualifies the
Technical Information. Readers are advised that mineral resources that are
not mineral reserves do not have demonstrated economic viability. The
Disclosure Documents are each intended to be read as a whole, and sections
should not be read or relied upon out of context. The Technical Information
is subject to the assumptions and qualifications contained in the Disclosure
Documents. The following employees of Capstone, each a Qualified Person,
reviewed Technical Information contained in this news release:
(1) Non-GAAP Performance Measures
"Total Cash Cost per Pound of Payable Copper" and "On site operating costs per tonne milled" are Non-GAAP Performance Measures. These performance measures are included because these statistics are key performance measures that management uses to monitor performance. Management uses these statistics to assess how the Company is performing to plan and to assess the overall effectiveness and efficiency of mining operations. These performance measures do not have a meaning within GAAP and, therefore, amounts presented may not be comparable to similar data presented by other mining companies. These performance measures should not be considered in isolation as a substitute for measures of performance in accordance with GAAP.
For further information: about Capstone, please contact:
SOURCE Capstone Mining Corp.
Source: PR Newswire
Related Articles
- Cimarex Announces First-Quarter Production Volumes and Provides Operations Update
- Western Goldfields Announces First Quarter Production and Status of the New Gold Business Combination
- Northgate Minerals Exceeds First Quarter Production Forecast
- Western Goldfields Announces 2009 Outlook and Fourth Quarter Production Update for the Mesquite Mine
- New Gold Announces Third Quarter Production Results and Cash Cost in Line With Annual Guidance
- Western Goldfields Announces Improved Mine Plan for Mesquite, Releases Third Quarter Production Results, and Revises Full-Year Production Target
- Patriot Coal Provides Update on Third Quarter Production
- Western Goldfields Second Quarter Production on Target
- FX Energy Gives Second Half 2007 Operations Update; Provides Fourth Quarter Production Estimate
- Ivernia Inc. Reports Its Highest Quarterly Production
User Comments (0)

RSS Feeds