Great Basin Provides Fourth Quarter Operational and Financial Update
Great Basin incurred an estimated loss of
At Hollister, ore tons and gold equivalent ounces extracted from trial mining activities during the fourth quarter were lower than planned due to several factors including more difficult mining conditions and an approximately two week suspension of trial mining in order to review the causes of, and take corrective action in connection with a worker falling accident during November which, fortunately, resulted in only a minor injury. A total of 16,785 tons of ore containing 20,660 Au eqv oz(1) were extracted which is, nevertheless, a 15% improvement over the third quarter of 2009. A total of 81,211 Au eqv oz was extracted over the 2009 year. Cash costs per ton mined for the quarter were adversely impacted by the lower than planned tonnage; however, good progress was still made on reducing the operating costs, and the cash cost per ore ton extracted from underground improved 12% from
A total of 161,518 Au eqv oz has been extracted at Hollister since the commencement of trial-mining activities in
Following the first phase of refurbishment and commissioning of the Esmeralda mill in
No revenue was booked during the fourth quarter and, as a result, the Hollister ore stockpile at
At Burnstone, good progress continues to be made with the development of surface and underground infrastructure. As at
The initial long hole stoping trials have delivered positive results thus far, and the Company plans to implement this higher level of mechanized mining on a trial basis over a period of 9 to 12 months before final evaluation. The current focus is the establishment of more mining stopes in Block B, with activities in Block C mainly focused on reef development. At
Sinking of the vertical shaft at Burnstone has continued and, at
The refurbishment of the Burnstone mills continues to be on schedule. All civil construction for the metallurgical plant facility will have been completed by
President and CEO
Overall, the Company continues to make good progress at both its gold development projects. Burnstone, in particular, is entering an extremely exciting phase of its development, with vertical shaft, mills and metallurgical plant converging on completion over the next several months.”
Johan Oelofse, Pr.Eng., FSAIMM, Chief Operating Officer of Great Basin and a Qualified Person, as defined by regulatory policy, has reviewed and assumed responsibility for the technical information contained in this release.
President and CEO
No regulatory authority has approved or disapproved the information contained in this news release.
Cautionary and Forward Looking Statement Information
This document contains “forward-looking statements” that were based on Great Basin’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.
Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These include but are not limited to:
- uncertainties and costs related to the Company's exploration and
development activities, such as those associated with determining
whether mineral resources or reserves exist on a property;
- uncertainties related to feasibility studies that provide estimates
of expected or anticipated costs, expenditures and economic returns
from a mining project; uncertainties related to expected production
rates, timing of production and the cash and total costs of
production and milling;
- uncertainties related to the ability to obtain necessary licenses,
permits, electricity, surface rights and title for development
projects;
- operating and technical difficulties in connection with mining
development activities;
- uncertainties related to the accuracy of our mineral reserve and
mineral resource estimates and our estimates of future production and
future cash and total costs of production, and the geotechnical or
hydrogeological nature of ore deposits, and diminishing quantities or
grades of mineral reserves;
- uncertainties related to unexpected judicial or regulatory
proceedings;
- changes in, and the effects of, the laws, regulations and government
policies affecting our mining operations, particularly laws,
regulations and policies relating to
- mine expansions, environmental protection and associated
compliance costs arising from exploration, mine development, mine
operations and mine closures;
- expected effective future tax rates in jurisdictions in which our
operations are located;
- the protection of the health and safety of mine workers; and
- mineral rights ownership in countries where our mineral deposits
are located, including the effect of the Mineral and Petroleum
Resources Development Act (South Africa);
- changes in general economic conditions, the financial markets and in
the demand and market price for gold, silver and other minerals and
commodities, such as diesel fuel, coal, petroleum coke, steel,
concrete, electricity and other forms of energy, mining equipment,
and fluctuations in exchange rates, particularly with respect to the
value of the U.S. dollar, Canadian dollar and South African rand;
- unusual or unexpected formation, cave-ins, flooding, pressures, and
precious metals losses (and the risk of inadequate insurance or
inability to obtain insurance to cover these risks);
- changes in accounting policies and methods we use to report our
financial condition, including uncertainties associated with critical
accounting assumptions and estimates;
- environmental issues and liabilities associated with mining including
processing and stock piling ore;
- geopolitical uncertainty and political and economic instability in
countries which we operate; and
- labour strikes, work stoppages, or other interruptions to, or
difficulties in, the employment of labour in markets in which we
operate mines, or environmental hazards, industrial accidents or
other events or occurrences, including third party interference that
interrupt the production of minerals in our mines.
For further information on Great Basin, investors should review the Company’s annual Form 20-F filing with the United States Securities and Exchange Commission www.sec.com and home jurisdiction filings that are available at www.sedar.com. The Company undertakes no obligation to update forward-looking information if circumstances or management’s estimates or opinions should change except as required by law.
Cautionary Note regarding Non-GAAP Measurements
Cash cost per ounce produced is a not a generally accepted accounting principles (“GAAP”) based figure but rather is intended to serve as a performance measure providing some indication of the mining and processing efficiency and effectiveness of test mining at the Hollister project. It is determined by dividing the relevant mining and processing costs excluding royalties by the ounces produced in the period. There may be some variation in the method of computation of “cash cost per ounce produced” as determined by the Company compared with other mining companies. In this context, “ounces produced” includes in-process and dore inventory along with ounces of gold sold in the period. Cash costs per ounce produced may vary from one period to another due to operating efficiencies, waste to ore ratios, grade of ore processed and gold recovery rates in the period. We provide this measure to our investors to allow them to also monitor operational efficiencies of test mining at Hollister. As a Non-GAAP Financial Measures cash cost per ounce should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP. There are material limitations associated with the use of such Non-GAAP measures.
----------------------------
(1) Gold equivalent ounces used here, and elsewhere in this document, was calculated using a gold price of
SOURCE Great Basin Gold Ltd.
