Part of Boston "Big Dig" tunnel collapses, kills 1

Posted on: Tuesday, 11 July 2006, 14:07 CDT

By Jason Szep

BOSTON (Reuters) - A three-tonne chunk of concrete fell from a tunnel ceiling in Boston's $14-billion "Big Dig" project, killing a woman in a car and rekindling questions over the safety of the nation's biggest public works venture.

Faulty steel beams called "tiebacks" that hold up 40-foot (12-meter) concrete ceiling panels gave way, causing four to six panels to fall, including one that crushed the roof of a Honda sedan at about 11 p.m. (0300 GMT) on Monday, said state authorities.

Milena Delvalle, 38, was killed instantly and her 46-year-old husband Angel suffered minor injuries.

The accident in the Interstate 90 connector tunnel is the latest problem to mar the "Big Dig," a 15-year project plagued by leaks and cost overruns that was designed to replace outdated elevated highways with a sleek system of tunnels.

The project has been compared to the Hoover Dam or the Panama Canal but it has also been criticized for cost overruns.

The Massachusetts Turnpike Authority, which oversaw the tunnel's construction, said the fallen panels had been built in 1999 and were inspected every two years.

"It's a horrible, horrible tragedy," MTA chairman Matt Amorello told reporters. "We will leave no stone unturned and no expense spared in pursuing any wrongdoing that may have occurred in the installation of these ceiling panels."

The tunnel was closed on Tuesday morning, choking rush hour traffic across Boston with some commuters delayed by more than an hour as police and engineers cordoned off the connector, which leads to the Ted Williams Tunnel and Boston's airport.

Amorello said state police were investigating and vowed to get to the bottom of why the beams gave way in a 200-ft (61 meter) section that forms the tunnel's air-ventilation system.

He said panels along that section of the tunnel would be removed and inspected and the connector tunnel would partially reopen to traffic by midday on Wednesday.

TWISTED STEEL

A witness told Boston's WBZ radio that chunks of concrete along with pieces of twisted steel tumbled from the ceiling.

The last piece of major "Big Dig" construction was finished this year, but some construction is still being done.

In May, six men who supplied concrete to the Big Dig were arrested and accused of delivering sub-standard materials to the project.

In April 2005, a day after federal officials declared the Big Dig's tunnels safe, debris fell from an overhead vent in a southbound tunnel and damaged at least five vehicles.

Former state Inspector General Robert Cerasoli, whose December 1998 report questioned the safety of construction in the Big Dig's Ted Williams tunnel, said he saw the accident coming.

"I did many many reports on this project over the course of 10 years and found a lot of shoddy work, construction work," he told New England Cable News.

"It is a direct result of doing a design-build project with such a large amount of money," he said. "The architect and the engineer watch over the people who construct it. They are on the same team. They are going to cover for each other."


Source: REUTERS

More News in this Category


Related Articles



Rating: 2.6 / 5 (9 votes)
Rate this article:
1/52/53/54/55/5

User Comments (0)

Comment on this article

Your Name
Text from the image
Comment
max 1200 chars
* All fields are required