2012-11-19 08:30:02

LOS ANGELES, Nov. 19, 2012 /PRNewswire/ -- The City of Victorville reached a settlement with Carter & Burgess after the end of a closed session meeting on November 9, 2012. The City will collect $54 Million that will cover virtually all damages incurred from the failed Foxborough Cogeneration Power Plant in which Carter and Burgess acted as the Design Engineer, Owner's Engineer and Construction Manager. Carter & Burgess appealed the decision, but ultimately made several...